Create a Baseline

Learn how to set a baseline to track deviations from your original timeline

Updated on January 4th, 2024

A baseline is like a snapshot of your original timeline. The baseline can be created once you've placed all your stages, tasks, dependencies and milestones on your timeline.

 

The baseline:

 

  • gives you a handy visual of any deviations from the timeline
  • can't be altered, so will always be a true representation of the original timeline
  • can easily be hidden, displayed on its own, or exported as required.

In the above image, the pale orange bars represent the baseline. The task called 'Variation: Increase Overhang' has caused a 1-day delay, as indicated by the red text. Our milestones (pink diamonds) have been duplicated in a paler shade; the paler diamonds will remain where they are, even if you move the milestone later.

 

 

Create a baseline

Weekend days
Before you create your baseline, decide whether you want to include weekend days in your timeline or not. If you create a baseline with Work on Weekends ticked and then you untick it, some tasks will appear as overdue.

 

 

To create a baseline:

  1. Open your project and click the Gantt Chart tab. If you haven't already created your Gantt chart, click Create Gantt chart view.
  2. Set all your dates so your timeline is how you need it, either including or excluding weekend days as required.
  3. Click Baseline > Create baseline > OK

The Baseline appears, and the Task Worksheet shows the Baseline Dates.

Baseline view

 
 

Task Worksheet Baseline

 
 

 

Baseline options

Once you've created your baseline, you'll see additional options in the Baseline dropdown menu. Click the links below to learn what each one does.

Hide baseline

This option hides the baseline from view, to keep your Gantt chart timeline looking cleaner for your everyday work. Click Baseline > Show Baseline to restore the baseline to the view.

 
 

Show baseline only

This option hides the adjustable elements of the timeline, i.e. task bars, stage bars, and dependencies. To restore these elements to the view, click Baseline > Show all.

 
 

Delete baseline

When you click Delete baseline, AroFlo asks you to confirm the deletion. This is because deleting the baseline cannot be reversed.

If you delete a baseline in error, you can create a new version by immediately clicking Baseline > Create baseline. As long as you haven't changed anything on the timeline, the new baseline will resemble the one that was deleted.

 
 
 

Need to export your chart?

The Gantt chart's Export feature creates a PDF, image (PNG) or CSV version of whatever is visible on your chart. You can export your chart with or without the baseline showing, or with only the baseline showing. See Export a Gantt Chart for more information.

 

 

What to do next

Now that your Gantt chart is all set up, it's time to start scheduling the work. See Schedule Project Tasks to learn how to schedule from within the Gantt chart, and see Track Progress to learn how to display project progress on your chart.