A baseline is like a snapshot of your original timeline. The baseline can be created once you've placed all your stages, tasks, dependencies and milestones on your timeline.
The baseline:
- gives you a handy visual of any deviations from the timeline
- can't be altered, so will always be a true representation of the original timeline
- can easily be hidden, displayed on its own, or exported as required.
Create a baseline
Weekend days
Before you create your baseline, decide whether you want to include weekend days in your timeline or not. If you create a baseline with Work on Weekends ticked and then you untick it, some tasks will appear as overdue.
To create a baseline:
- Open your project and click the Gantt Chart tab. If you haven't already created your Gantt chart, click Create Gantt chart view.
- Set all your dates so your timeline is how you need it, either including or excluding weekend days as required.
Click Baseline > Create baseline > OK.
The Baseline appears, and the Task Worksheet shows the Baseline Dates.
Baseline options
Once you've created your baseline, you'll see additional options in the Baseline dropdown menu. Click the links below to learn what each one does.
This option hides the baseline from view, to keep your Gantt chart timeline looking cleaner for your everyday work. Click Baseline > Show Baseline to restore the baseline to the view.
This option hides the adjustable elements of the timeline, i.e. task bars, stage bars, and dependencies. To restore these elements to the view, click Baseline > Show all.
When you click Delete baseline, AroFlo asks you to confirm the deletion. This is because deleting the baseline cannot be reversed.
Need to export your chart?
The Gantt chart's Export feature creates a PDF, image (PNG) or CSV version of whatever is visible on your chart. You can export your chart with or without the baseline showing, or with only the baseline showing. See Export a Gantt Chart for more information.
What to do next
Now that your Gantt chart is all set up, it's time to start scheduling the work. See Schedule Project Tasks to learn how to schedule from wtihin the Gantt chart, and see Track Progress to learn how to display project progress on your chart.
-